Fernandina Harbor Marina update: August 2, 2019

Posted

Submitted by Suanne Z. Thamm

Reporter - News Analyst

August 2, 2019 - 2:30 p.m.

Installation of south basin attenuator is underway.

Dock 4, south basin

Fernandina Beach City Manager Dale Martin has advised that despite the rainy weather, today work began to install the south basin attenuator, and utility work will begin next week.

Martin also reports that in the south basin, Dock 4 installation is complete.  Dock 5 was also installed, but additional work is required.  Dock 6 is on site and will be installed in conjunction with the attenuator.

Coordination with FEMA continues regarding the North Attenuator.

Fernandina Harbor Marina