Southern attenuator docks under construction

Submitted by Suanne Z. Thamm
Reporter – News Analyst
May 20, 2019 4:01 p.m.

Fernandina Beach City Manager Dale Martin has provided a link to a Fender YouTube video to help chart the progress of repairs to the south basin of the Fernandina Harbor Marina.

Martin reports that dredging operations and piling removal are nearly complete in the south basin. The Florida Inland Navigation District (FIND) site work has been completed. Plans for dredge materials to be removed are under development.

Coordination with FEMA continues on repairs to the northern attenuator. Bid package ITB 2019-07  for installation of pilings, docks, fuel, fire, and electrical systems has been posted, and bids are due Jun 4.